- 310 registry:skill items, 1528 files, 7 categories (hub tags) - registry.json generated by @kortix/registry buildRegistry - nested SKILL.md in sn-da-* renamed SUBSKILL.md (no phantom skills) - provenance + licenses: SOURCES.md
222 lines
10 KiB
Markdown
222 lines
10 KiB
Markdown
---
|
|
name: close-management
|
|
description: Manage the month-end close process with task sequencing, dependencies, and status tracking. Use when planning the close calendar, tracking close progress, identifying blockers, or sequencing close activities by day.
|
|
user-invocable: false
|
|
---
|
|
|
|
# Close Management
|
|
|
|
**Important**: This skill assists with close management workflows but does not provide financial advice. All close activities should be reviewed by qualified financial professionals.
|
|
|
|
Month-end close checklist, task sequencing and dependencies, status tracking, and common close activities organized by day.
|
|
|
|
## Month-End Close Checklist
|
|
|
|
### Pre-Close (Last 2-3 Business Days of the Month)
|
|
|
|
- [ ] Send close calendar and deadline reminders to all contributors
|
|
- [ ] Confirm cut-off procedures with AP, AR, payroll, and treasury
|
|
- [ ] Verify all sub-systems are processing normally (ERP, payroll, banking)
|
|
- [ ] Complete preliminary bank reconciliation (all but last-day activity)
|
|
- [ ] Review open purchase orders for potential accrual needs
|
|
- [ ] Confirm payroll processing schedule aligns with close timeline
|
|
- [ ] Collect information for any known unusual transactions
|
|
|
|
### Close Day 1 (T+1: First Business Day After Month-End)
|
|
|
|
- [ ] Confirm all sub-ledger modules have completed period-end processing
|
|
- [ ] Run AP accruals for goods/services received but not invoiced
|
|
- [ ] Post payroll entries and payroll accrual (if pay period straddles month-end)
|
|
- [ ] Record cash receipts and disbursements through month-end
|
|
- [ ] Post intercompany transactions and confirm with counterparties
|
|
- [ ] Complete bank reconciliation with final bank statement
|
|
- [ ] Run fixed asset depreciation
|
|
- [ ] Post prepaid expense amortization
|
|
|
|
### Close Day 2 (T+2)
|
|
|
|
- [ ] Complete revenue recognition entries and deferred revenue adjustments
|
|
- [ ] Post all remaining accrual journal entries
|
|
- [ ] Complete AR subledger reconciliation
|
|
- [ ] Complete AP subledger reconciliation
|
|
- [ ] Record inventory adjustments (if applicable)
|
|
- [ ] Post FX revaluation entries for foreign currency balances
|
|
- [ ] Begin balance sheet account reconciliations
|
|
|
|
### Close Day 3 (T+3)
|
|
|
|
- [ ] Complete all balance sheet reconciliations
|
|
- [ ] Post any adjusting journal entries identified during reconciliation
|
|
- [ ] Complete intercompany reconciliation and elimination entries
|
|
- [ ] Run preliminary trial balance and income statement
|
|
- [ ] Perform preliminary flux analysis on income statement
|
|
- [ ] Investigate and resolve material variances
|
|
|
|
### Close Day 4 (T+4)
|
|
|
|
- [ ] Post tax provision entries (income tax, sales tax, property tax)
|
|
- [ ] Complete equity roll-forward (stock compensation, treasury stock)
|
|
- [ ] Finalize all journal entries — soft close
|
|
- [ ] Generate draft financial statements (P&L, BS, CF)
|
|
- [ ] Perform detailed flux analysis and prepare variance explanations
|
|
- [ ] Management review of financial statements and key metrics
|
|
|
|
### Close Day 5 (T+5)
|
|
|
|
- [ ] Post any final adjustments from management review
|
|
- [ ] Finalize financial statements — hard close
|
|
- [ ] Lock the period in the ERP/GL system
|
|
- [ ] Distribute financial reporting package to stakeholders
|
|
- [ ] Update forecasts/projections based on actual results
|
|
- [ ] Conduct close retrospective — identify process improvements
|
|
|
|
## Task Sequencing and Dependencies
|
|
|
|
### Dependency Map
|
|
|
|
Tasks are organized by what must complete before the next task can begin:
|
|
|
|
```
|
|
LEVEL 1 (No dependencies — can start immediately at T+1):
|
|
├── Cash receipts/disbursements recording
|
|
├── Bank statement retrieval
|
|
├── Payroll processing/accrual
|
|
├── Fixed asset depreciation run
|
|
├── Prepaid amortization
|
|
├── AP accrual preparation
|
|
└── Intercompany transaction posting
|
|
|
|
LEVEL 2 (Depends on Level 1 completion):
|
|
├── Bank reconciliation (needs: cash entries + bank statement)
|
|
├── Revenue recognition (needs: billing/delivery data finalized)
|
|
├── AR subledger reconciliation (needs: all revenue/cash entries)
|
|
├── AP subledger reconciliation (needs: all AP entries/accruals)
|
|
├── FX revaluation (needs: all foreign currency entries posted)
|
|
└── Remaining accrual JEs (needs: review of all source data)
|
|
|
|
LEVEL 3 (Depends on Level 2 completion):
|
|
├── All balance sheet reconciliations (needs: all JEs posted)
|
|
├── Intercompany reconciliation (needs: both sides posted)
|
|
├── Adjusting entries from reconciliations
|
|
└── Preliminary trial balance
|
|
|
|
LEVEL 4 (Depends on Level 3 completion):
|
|
├── Tax provision (needs: pre-tax income finalized)
|
|
├── Equity roll-forward
|
|
├── Consolidation and eliminations
|
|
├── Draft financial statements
|
|
└── Preliminary flux analysis
|
|
|
|
LEVEL 5 (Depends on Level 4 completion):
|
|
├── Management review
|
|
├── Final adjustments
|
|
├── Hard close / period lock
|
|
├── Financial reporting package
|
|
└── Forecast updates
|
|
```
|
|
|
|
### Critical Path
|
|
|
|
The critical path determines the minimum close duration. Typical critical path:
|
|
|
|
```
|
|
Cash/AP/AR entries → Subledger reconciliations → Balance sheet recs →
|
|
Tax provision → Draft financials → Management review → Hard close
|
|
```
|
|
|
|
To shorten the close:
|
|
- Automate Level 1 entries (depreciation, prepaid amortization, standard accruals)
|
|
- Pre-reconcile accounts during the month (continuous reconciliation)
|
|
- Parallel-process independent reconciliations
|
|
- Set clear deadlines with consequences for late submissions
|
|
- Use standardized templates to reduce reconciliation prep time
|
|
|
|
## Status Tracking and Reporting
|
|
|
|
### Close Status Dashboard
|
|
|
|
Track each close task with the following attributes:
|
|
|
|
| Task | Owner | Deadline | Status | Blocker | Notes |
|
|
|------|-------|----------|--------|---------|-------|
|
|
| [Task name] | [Person/role] | [Day T+N] | Not Started / In Progress / Complete / Blocked | [If blocked, what's blocking] | [Any notes] |
|
|
|
|
### Status Definitions
|
|
|
|
- **Not Started:** Task has not yet begun (may be waiting on dependencies)
|
|
- **In Progress:** Task is actively being worked on
|
|
- **Complete:** Task is finished and has been reviewed/approved
|
|
- **Blocked:** Task cannot proceed due to a dependency, missing data, or issue
|
|
- **At Risk:** Task is in progress but may not meet its deadline
|
|
|
|
### Daily Close Status Meeting (Recommended)
|
|
|
|
During the close period, hold a brief (15-minute) daily standup:
|
|
|
|
1. **Review status board:** Walk through open tasks, flag any that are behind
|
|
2. **Identify blockers:** Surface any issues preventing task completion
|
|
3. **Reassign or escalate:** Adjust ownership or escalate blockers to resolve quickly
|
|
4. **Update timeline:** If any tasks are at risk, assess impact on overall close timeline
|
|
|
|
### Close Metrics to Track Over Time
|
|
|
|
| Metric | Definition | Target |
|
|
|--------|-----------|--------|
|
|
| Close duration | Business days from period end to hard close | Reduce over time |
|
|
| # of adjusting entries after soft close | Entries posted during management review | Minimize |
|
|
| # of late tasks | Tasks completed after their deadline | Zero |
|
|
| # of reconciliation exceptions | Reconciling items requiring investigation | Reduce over time |
|
|
| # of restatements / corrections | Errors found after close | Zero |
|
|
|
|
## Common Close Activities by Day
|
|
|
|
### Typical 5-Day Close Calendar
|
|
|
|
| Day | Key Activities | Responsible |
|
|
|-----|---------------|-------------|
|
|
| **T+1** | Cash entries, payroll, AP accruals, depreciation, prepaid amortization, intercompany posting | Staff accountants, payroll |
|
|
| **T+2** | Revenue recognition, remaining accruals, subledger reconciliations (AR, AP, FA), FX revaluation | Revenue accountant, AP/AR, treasury |
|
|
| **T+3** | Balance sheet reconciliations, intercompany reconciliation, eliminations, preliminary trial balance, preliminary flux | Accounting team, consolidation |
|
|
| **T+4** | Tax provision, equity roll-forward, draft financial statements, detailed flux analysis, management review | Tax, controller, FP&A |
|
|
| **T+5** | Final adjustments, hard close, period lock, reporting package distribution, forecast update, retrospective | Controller, FP&A, finance leadership |
|
|
|
|
### Accelerated Close (3-Day Target)
|
|
|
|
For organizations targeting a faster close:
|
|
|
|
| Day | Key Activities |
|
|
|-----|---------------|
|
|
| **T+1** | All JEs posted (automated + manual), all subledger reconciliations, bank reconciliation, intercompany reconciliation, preliminary trial balance |
|
|
| **T+2** | All balance sheet reconciliations, tax provision, consolidation, draft financial statements, flux analysis, management review |
|
|
| **T+3** | Final adjustments, hard close, reporting package, forecast update |
|
|
|
|
**Prerequisites for a 3-day close:**
|
|
- Automated recurring journal entries (depreciation, amortization, standard accruals)
|
|
- Continuous reconciliation during the month (not all at month-end)
|
|
- Automated intercompany elimination
|
|
- Pre-close activities completed before month-end (cut-off, accrual estimates)
|
|
- Empowered team with clear ownership and minimal handoffs
|
|
- Real-time or near-real-time sub-system integration
|
|
|
|
## Close Process Improvement
|
|
|
|
### Common Bottlenecks and Solutions
|
|
|
|
| Bottleneck | Root Cause | Solution |
|
|
|-----------|-----------|---------|
|
|
| Late AP accruals | Waiting for department spend confirmation | Implement continuous accrual estimation; set cut-off deadlines |
|
|
| Manual journal entries | Recurring entries prepared manually each month | Automate standard recurring entries in the ERP |
|
|
| Slow reconciliations | Starting from scratch each month | Implement continuous/rolling reconciliation |
|
|
| Intercompany delays | Waiting for counterparty confirmation | Automate intercompany matching; set stricter deadlines |
|
|
| Management review changes | Large adjustments found during review | Improve preliminary review process; empower team to catch issues earlier |
|
|
| Missing supporting documents | Scrambling for documentation at close | Maintain documentation throughout the month |
|
|
|
|
### Close Retrospective Questions
|
|
|
|
After each close, ask:
|
|
1. What went well this close that we should continue?
|
|
2. What took longer than expected and why?
|
|
3. What blockers did we encounter and how can we prevent them?
|
|
4. Were there any surprises in the financial results we should have caught earlier?
|
|
5. What can we automate or streamline for next month?
|